PROCESS OUTLINE

Seven phases of Full Architectural Service:

1. Pre-Design
2. Schematic Design
3. Design Development
4. Construction Documents
5. Bidding and Negotiations
6. Construction Administration
7. Post-Occupancy Evaluation


1. Pre-Design

  • Code, Zoning and Historical Analysis
  • Programming
  • Existing Conditions Analysis
    • Site Analysis
    • Existing dwelling documentation
  • Adjacency Study or Blocking/Bubble diagrams

(back to top)

2. Schematic Design

  • Concept Generation
  • Plan generation and study
    • Analyze circulation and egress
    • Analyze Solar orientation and daylighting issues
    • Analyze MEP and fireprotection constraints on generated plan.
  • Exterior Elevation and building sections generation and study
  • Integration of site/existing conditions/local regulations considerations
  • Three dimensional model, if required.

(back to top)

3. Design Development

  • Expand general plans, sections and elevations
  • Addressing of owner concerns
  • Detail generation
    • Casework
    • Millwork
    • Architectural detailing
  • Selection of Finishes:
    • Interior
    • Exterior
  • Expansion of functional issues analysis
    • heating and cooling options
    • plumbing considerations
    • structural systems
    • communications cabling
    • lighting systems
    • low maintenance materials
    • site issues
  • Initial analysis of Construction Costs

(back to top)

4. Construction Documents

  • Generation of legal drawings depicting the complete scope of the project, also including:
    • Building Plans
    • Sections
    • Elevations
    • Details
    • Site plans
    • Reflected ceiling plans
    • Furniture layouts plans
    • Interior elevations
  • Coordination and integration of Civil, Landscaping, Structural, MEP and Fire-Proofing construction documents
  • Coordination and integration of all pertinent Consultant Plans including:
    • Furniture
    • Lighting
    • Interior design
    • Acoustical
  • Generation of materials and procedures specification
    • 16 Divisions
      • 01 General Data
      • 02 Site Construction
      • 03 Concrete
      • 04 Masonry
      • 05 Metals
      • 06 Wood & Plastics
      • 07 Thermal & Moisture Protection
      • 08 Doors & Windows
      • 09 Finishes
      • 10 Specialties
      • 11 Equipment
      • 12 Furnishings
      • 13 Special Construction
      • 14 Conveying Systems15 Mechanical
      • 16 Electrical
  • Update to Construction Budget
    • Preliminary release of documents to preferred contractors for pricing evaluation,
    • Professional Estimator services

(back to top)

5. Bidding and Negotiations

  • Invitation to qualified bid list to submit pricing
  • Distribution of Construction Documents and Specifications
  • Evaluation of submitted bids
    • Discard highest and lowest bid
  • Awarding of contract to most competitive bidder
  • Value Engineering to re-align construction budget

(back to top)

6. Construction Administration

  • Monitor Construction progress of project
  • Approve shop drawings
  • Document meeting minutes
  • Review payment requisitions
  • Issue change-orders with related clarification sketches as required
  • Conduct punch-list
    • Approve repairs
    • Review final payment requisition
  • Assist with project close-out

(back to top)

7. Post-Occupancy Evaluation

  • Conduct Post-Occupancy Evaluation
  • Evaluate how facility is used versus how it was designed to be used.
  • Evaluate energy consumption and efficiency of MEP systems.

(back to top)